Hurricane Sandy Waterway Debris

Southern Region
To Date:
  • Total cubic yards of debris removed: 3,575.9 cubic yards.
  • Total verified acres surveyed by side-scan sonar: 7,004 acres (not yet verified)
Today’s Operations:
  • Low water hindered operations at Flat Island and High Island today.
  • Targets were recovered in the Great Bay Marina, which is now considered complete of visual and targeted debris. A total of 129 cubic yards of debris were recovered today.
Forecasted Operations:
  • Debris recovery will continue at Flat Island and High Island, as well as Mystic Island between Twin Lakes Road and Radio Road.
  • Maurice River debris recovery will continue and is expected to be completed of visual and targeted debris over the weekend.
Report debris at 1-877-WARN-DEP